Automated Warehouse Systems Integration

The success of a big project hinges on how well individual parts, and the people responsible for them, come together as a whole


Companies positioned for growth often face a strange dilemma. The prospect of retrofitting, expanding or building a new facility is good news, but then comes the hard work of moving between operations as they are and operations as they could be. Multi-million dollar projects promise increased capabilities, but also threaten calamitous failure.

Successfully navigating a new project does not have to be an act of faith. While many risks cannot be avoided, most can be anticipated, and careful planning from the first day can ensure minimal disruption and maximum results. System integrators, designers and consultants agree that the most important concept, without which a project is much less likely to succeed, is internal ownership.

“If all the right people are involved from day one, you’re basically assuring internal ownership,”Bob Ouellette, a partner with The Progress Group.

“If all the right people are involved from day one, you’re basically assuring internal ownership” says Bob Ouellette, a partner with The Progress Group. “A project team should not be made purely of corporate engineering, without operational, financial and customer service people in the room. The idea of change management starting when the project gets going is way, way too late.”

Building the right team and defining clear roles for employees, integrators and suppliers is essential, from the first meeting to design, testing, go-live and auditing. In an effort to help break the process down into manageable pieces, Modern spoke to a few industry integrators about what end-users can expect throughout the course of a project.

Making the case and building the team
It all begins with a project champion: Someone who acts as the single point of contact between executives responsible for the project, oversees the project from initiation to execution, and who is critical to a project’s success. In building the business case for a project, the champion must be sure to articulate its impact and value to all stakeholders in an organization. From the very beginning, it’s important that the champion sets realistic expectations, says John Hill, director at St. Onge Company.

“If the plan is to cut costs by 25% and increase throughput by 30%, I’d take a real hard look at those numbers”John Hill, St. Onge Company

“If the plan is to cut costs by 25% and increase throughput by 30%, I’d take a real hard look at those numbers,” Hill says. “If you oversell the results to colleagues and management, it can really impact morale.”

The project champion must also prepare the organization for change by conveying the hard work required to ensure success. Ouellette says change management is not the same as change avoidance and adds that “one of the biggest misconceptions is that you can just buy a system and have an integrator drop it in.”

In fact, says Hill, the amount of work for the end user is at least double what the system integrator will do. As soon as possible, he says, the champion should begin building organizational charts, assigning key roles, and planning for certain employees to be tied up in testing and training at specific points in the implementation. This process can identify which strengths a company can bring to the table and which roles they might look to an integrator to provide.

To bid or not to bid
With the business case established and the internal team in place, it’s time to find a system integrator that can become a trusted partner, not simply a supplier of a service.

“Often, the customer will put together the base RFP and ask for prices,” says Larry Boroff, director of automation systems engineering for Forte. “Requirements in an RFP can be read in a lot of ways, and that’s simply not enough up-front conversation to isolate what they have, what they need and what they’re getting.”

“Requirements in an RFP can be read in a lot of ways, and that’s simply not enough up-front conversation to isolate what they have, what they need and what they’re getting.”Larry Boroff, director of automation systems engineering for Forte

According to Ed Jones, manager of integrated systems for TranSystems, some are bound by corporate policy to go through the bid process. Some can transcend that corporate policy with careful team-building, and others build dynamic teams only to hand it over to purchasing to select the cheapest bid.

“For any project, keeping the cost to the absolute bare-bones is not the objective,” says Jones. “The objective is fulfilling a vision.”

Customers should look for integrators with the appropriate skill sets and relevant experience, with an eye toward choosing a program manager, not just a project manager. Those are two different things, according to John Giangrande, senior account executive at Fortna. Project managers for construction, software and materials handling equipment are responsible for each of those work streams and the associated budgets and resources, he says. “The program manager sits on top of those managers,” says Giangrande. “They are very distinct job descriptions.”

Scheduling and risk assessment
Having selected an integration partner, it’s time to create the skeletal timeline of a project. The road map should have tasks, with a schedule and budget for each. “Scheduling is an evolving process throughout the project,” says Jones. “A lot of operations people don’t want to hear that.” Risk assessments should begin in the first week of a project, and should be revisited regularly.

“For any project, keeping the cost to the absolute bare-bones is not the objective,”Ed Jones, manager of integrated systems for TranSystems

Ouellette recommends identifying the project’s “anchors,” those deadlines or constraints that absolutely cannot change, and conducting a trade-off analysis. “When working with retailers, for instance, the last thing you want to do is any start-up work after September,” he says.

Real estate is a common risk that can push a schedule way off course, says Ouellette. A zoning problem could extend the project schedule by a few months. In the case of a retailer who plans to have a project completed for the holiday season, it might not be possible to pick up where you left off once you resolve the real estate issues. A three-month delay could turn into a six- or nine-month delay.

In addition to identifying risk, it’s important to communicate who is responsible for reacting to risks as they escalate from green to yellow to red. “This can create a ‘fox in the hen house’ situation,” says Ouellette. “It’s a tough call to alert someone that you may have a problem, and it shouldn’t be the supplier who decides when the customer is in trouble.”

Bringing in suppliers
When suppliers are brought in, they should also be ready to review risks and schedules on a regular basis. Although it’s always good to stay focused on outcomes, it is rarely helpful to rush. Jones offers a favorite saying: “Fast, good or cheap. Choose any two.”

“You can’t just say, ‘we’ll have a packaging station here and deal with problems later, that station might only represent 2% of the project cost, but if there are problems there it represents 100% of product not getting billed.”John Giangrande, senior account executive at Fortna

“I don’t recommend contacting 20 suppliers and whittling it down from there,” he says. “Read, ask around, do your own research and get a good idea of who you’ll be using, then reach out to a small group.” Jones says the dynamic has changed from five or 10 years ago when customers had to go through suppliers to get introduced to prior customers and find anything out about their experience. “Now it’s more of a peer-to-peer networking and supplier evaluation process.”

With the top three suppliers selected, Hill suggests they come in, give a presentation to those who will be using the equipment, and also leave sample equipment for employees to experiment with and vote for. “If they were involved in the equipment selection,” asks Hill, “how can they complain?”

Designing and testing
When designing a system, every detail that can be addressed at the outset will prevent potential headaches later. Before positioning a workstation, for instance, determine whether it is 36 inches or 42 inches tall, where the printer will be and where the pen cup might fit. Fortna’s Giangrande recommends spending as much as five or six weeks on the detailed design, reviewing all touch points.

“You can’t just say, ‘we’ll have a packaging station here and deal with problems later,’” says Giangrande. “That station might only represent 2% of the project cost, but if there are problems there it represents 100% of product not getting billed.”

When planning for the future, says Forte’s Boroff, you might plan for a sorter to be expanded, or choose a lower-rate sorter and plan for the cost of installing a higher-rate sorter when the time comes. This is also a good time to consider how the new expansion or sorter will be installed with minimal disruption years from now.

“For both software and hardware tests, the end-user should provide business examples against which suppliers’ solutions can be tested very early”John Hill, St. Onge Company

After creating the right design, the most critical element of a project is testing, testing, testing. Ouellette says tests confirm the supplier has done the right thing, confirm that all the pieces are working together, and facilitate the training process. It’s also important for testing to be a team-based, continuous process, without overly relying on the big cut-over weekend to resolve issues. “Instead of building some code, letting it sit for eight months then working out bugs in a panic,” says Giangrande, “be testing it all along.”

For both software and hardware tests, the end-user should provide business examples against which suppliers’ solutions can be tested very early, says Hill. Specialized planning software can also overlay suppliers’ and contractors’ building plans to avoid conflicts. According to St. Onge research, says Hill, conflict-related change orders average $75,000 apiece, and can constitute 2% to 5% of the total project cost.

Tests should also be conducted for future rates and/or product types. The initial project might involve only building five of a potential 10 lanes, says Giangrande, but one can still test induction for that future capacity.

Going live and auditing
It is best to go live in portions. It is even more important to have a go-back plan, says Giangrande. “Anything can happen, from a wiring error to a lightning strike,” he says. “You want to be sure you can return to business as usual if necessary and try again another weekend.”

When auditing, look at whether design and reality meet, says Boroff, and be prepared to make adjustments in light of real-world tests. Materials break in, such as stretching belts, and an integrator and customer should plan for a period of on-site support following a cut-over, with extended support for as much as 90 to 120 days afterward.

Some integrators and customers will settle for getting a new system functional on cut-over weekend, with plans to dial in the rest once it’s up and running, says Jones, who says that approach can create problems. “They have suppliers in hotels nearby waiting all day to contribute for 15 minutes,” he says. “But at the same time, the customer is becoming less and less willing to shut down again to let them make the changes.”

The ultimate goal for the customer and integrator is to keep the customer running, says Boroff. “If something doesn’t work, or for some reason the rates are not there, it’s the responsibility of the integrator to stand behind their product and make it right.”

A dozen must-haves for integrated systems implementation

Analysis/Design/Planning

    1. 1. Assemble the right cross-functional team, with internal skills and external expertise. Gain early buy-in.
      2. Avoid defining the solution too early. Be led by the data and the analytics.
      3. Build a solution with low impact to the warehouse management system (legacy or new). This may require use of a warehouse control system.
      4. Identify and reconcile expectations into one set of business drivers and measures for success.

Business Case

    1. 5. Perform life cycle analysis to consider full costs to support the solution.
      6. Factor in real estate requirements, decisions and timing (zoning, permitting and build-out).

Partner Selection/Implementation

    1. 7. Consider proven solutions and recent relevant reference visits. This is part of the team’s due diligence.
      8. Pick the right type of integration partner that matches your team’s and project’s needs.
      9. Implement a lean project management office and cadence, with senior-level governance and one set of reports/dashboards.
      10. Conduct regular risk assessments and periodic “change readiness” evaluations.

Start-up/Go-Live

    1. 11. Create a rock-solid commissioning and testing plan, with full involvement from the business.
      12. Synchronize training, go-live and transition to achieve early benefits from each subsystem.

Article Topics


FORTNA News & Resources

Kathleen Phelps to join FORTNA as chief financial officer
How Automation and Software are Solving Supply Chain Productivity Challenges
FORTNA showcases OptiSweep solution  
Retail distribution closes in on the customer
FORTNA and Geek+ partner to speed order fulfillment with automated robotics solutions
Warehouse execution systems (WES) stretches to encompass labor
Predictive maintenance: Ready to launch
More FORTNA

Latest in Warehouse|DC

Spotlight Startup: Cart.com is Reimagining Logistics
Walmart and Swisslog Expand Partnership with New Texas Facility
Taking Stock of Today’s Robotics Market and What the Future Holds
U.S. Manufacturing Gains Momentum After Another Strong Month
Biden Gives Samsung $6.4 Billion For Texas Semiconductor Plants
Walmart Unleashes Autonomous Lift Trucks at Four High-Tech DCs
Plastic Pollution is a Problem Many Companies are Still Ignoring
More Warehouse|DC

About the Author

Josh Bond
Josh Bond was Senior Editor for Modern through July 2020, and was formerly Modern’s lift truck columnist and associate editor. He has a degree in Journalism from Keene State College and has studied business management at Franklin Pierce University.
Follow Logistics Management on FaceBook


Fortna helps Clients make and keep bold promises to their customers – fast, accurate and cost-effective fulfillment consistently at every touchpoint, across every channel. Fortna’s expertise spans distribution strategy, distribution center operations, material handling automation, supply chain systems and warehouse execution software systems.



View FORTNA company profile

 

Featured Downloads

GEP Procurement & Supply Chain Tech Trends Report 2024
GEP Procurement & Supply Chain Tech Trends Report 2024
We’ve researched the five biggest trends in the supply chain space this year, and, drawing on our expertise in procurement and...
Unified Control System - Intelligent Warehouse Orchestration
Unified Control System - Intelligent Warehouse Orchestration
Download this whitepaper to learn Unified Control System (UCS), designed to orchestrate automated and human workflows across the warehouse, enabling automation technologies...

An Inside Look at Dropshipping
An Inside Look at Dropshipping
Korber Supply Chain’s introduction to the world of dropshipping. While dropshipping is not for every retailer or distributor, it does provide...
C3 Solutions Major Trends for Yard and Dock Management in 2024
C3 Solutions Major Trends for Yard and Dock Management in 2024
What trends you should be focusing on in 2024 depends on how far you are on your yard and dock management journey. This...
Packsize on Demand Packing Solution for Furniture and Cabinetry Manufacturers
Packsize on Demand Packing Solution for Furniture and Cabinetry Manufacturers
In this industry guide, we’ll share some of the challenges manufacturers face and how a Right-Sized Packaging On Demand® solution can...